Jenganami
  • Home
  • Construction
  • Decor
  • House plans
    • Studio/Bedsit Plan
    • one bedroom plan
    • Two-Bedroom plan
    • Three bedroom plan
  • Construction Materials
  • Discover
  • Contact Us
Archives
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • May 2024
  • April 2024
  • April 2023
  • March 2023
  • February 2023
  • December 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • March 2022
  • February 2022
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
Categories
  • Construction
  • Construction Materials
  • Decor
  • Design
  • Discover
  • one bedroom plan
  • Studio/Bedsit Plan
  • Three bedroom plan
  • Two-Bedroom plan
Jenganami
Subscribe
Jenganami
  • Home
  • Construction
  • Decor
  • House plans
    • Studio/Bedsit Plan
    • one bedroom plan
    • Two-Bedroom plan
    • Three bedroom plan
  • Construction Materials
  • Discover
  • Contact Us
  • Construction
  • Discover

How to formally hand over a project

  • June 23, 2020
  • No comments
  • 3 minute read
Share
Tweet
Share
Share
Share

This blog offers a guideline for the steps that should be taken in order to officially hand over a site to the client upon completion of construction.
1. The main contractor in charge of execution must formally let the necessary parties, ie. the client and the architect/construction project manager or the responsible representatives that the construction is as per previously dictated terms, completed.

2. From the attached documents, images and other representations the construction project manager can start documenting completion for the project. This is important to note
because some warranties may come into effect and the contractor may claim completion at the time of submission of proof.

Handing over a project, Cytonn Photography, Unsplash



3. The construction project manager, client and client representatives visit the site and using a checklist or experience does a general check for all pre-dictated specification items from the drawings that need to be completed at the end of the said project. During this time, the project manager/architect/engineer should come up with a snag list that shows all the work that
requires fixing, extra attention or replacement.

4. The contractor comes up with a keying schedule for all the necessary areas and this is delivered to the client, properly itemised and thoroughly cross checked.

5. Submission of all the necessary documents that are required of the contractor is done as per the contract. These generally include, results from tests conducted, administrative paperwork, all variations made on site and the accompanying working drawings.

6. The contractor then works on the snag list prepared from the initial site visit and ensures that all the work is up to standard. A site visit is then arranged to make sure that all the work has been done to the satisfaction of the technical team and the client representative team.

Site Visit, Unsplash



7. The contractor can then submit all the required certificates, bonds and warranties that are required by the contract conditions. This will trigger the start of the final request for payment.

8. One the client/client representative accepts the work, the architect/construction project manager sends a certificate of completion to the contractor and a copy to the client. If there exists operating and maintenance documents for the project, these should at this point be forwarded to the architect/project manager who will share them with the client.

9. The contractor then makes the final payment request for the project. The payment request must include proof that all the subcontractors and the material providers who were involved in the project were paid. The payment request should also include all/ any variations that were not covered in the previous payment requests.

Handing over a project, Usplash



10. The construction project manager/ architect upon cross checking all the necessary documents sends the final certificate of payment to the client.
11. Where applicable, the contractor issues a certificate of occupancy from the local government to ensure that the authorities approve occupancy of the project for the intended use.

12. The client makes the final payment and notifies the construction project manager of this. This step is crucial and must be documented to ensure that the transfer of risk from the contractor to the client is done.

Hope this information has been useful. Build wisely!

Also read: Concreting checks

Share
Tweet
Pin it
Share
Share
Share
Aka Nakwa

Previous Article
  • Construction

Common quality checks for concrete during mixing, placing and curing

  • June 21, 2020
  • Aka Nakwa
View Post
Next Article
  • Construction
  • Discover

5 Ways to determine how much to charge for professional service

  • June 27, 2020
  • Aka Nakwa
View Post
You May Also Like
View Post
  • Construction Materials
  • Discover

What you need to know about Portable Back up power stations for emergency power.

  • Aka Nakwa
  • May 22, 2025
View Post
  • Discover

How much does it cost to install solar for a small home? What you need to know

  • Aka Nakwa
  • May 20, 2025
View Post
  • Decor
  • Discover
  • Three bedroom plan
  • Two-Bedroom plan

Amazing expandable home you can build with 1 Million Kenyan Shillings

  • Aka Nakwa
  • April 14, 2025
View Post
  • Discover

How to Start a Bedsitter Rental Business in Kenya

  • Aka Nakwa
  • April 3, 2025
View Post
  • Discover

Affordable Water storage solutions: Water pans

  • Aka Nakwa
  • March 14, 2025
View Post
  • Discover

Building affordable homes for rent, some hacks you should know.

  • Aka Nakwa
  • March 13, 2025
View Post
  • Construction

Floor finishes: Can you save money using power floating?

  • Aka Nakwa
  • March 10, 2025
View Post
  • Discover

Decent semi Permanent housing options available in the market today

  • Aka Nakwa
  • February 17, 2025

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Subscribe

Subscribe now to our newsletter

Jenganami
  • Home
  • Construction
  • Decor
  • House plans
  • Construction Materials
  • Discover
  • Contact Us
Your building Companion

Input your search keywords and press Enter.